June 9, 2011 - Framing Day One
The plan was to start framing yesterday but they were not able to get to it other than unpacking the lumber. The framing of our house begun today. They did more than we expected. We can't wait to see how much more framing they will do tomorrow before breaking for the weekend.
Sunday, June 5, 2011
June 1, 2011 - Dirt put back
The foundation is all finished up and the dirt is put back this week. The lumber is scheduled to arrive this friday. The plan is to start framing next week.
May 25, 2011 - Foundation Wall
As promised, the foundation wall poured this week. It looks great! The plan for the rest of this week is to have the foundation water proofed and have it ready for inspection early next week. Once the town inspect the foundation, they will be able to put back the dirt.
May 20, 2011 - Foundation Footing
The footing of the foundation poured this week. Looking at the foundation, we were able to make out the first floor. The plan for next week is to build the foundation wall. Things are progressing really well.
May 16, 2011 Ground Digging
It was exciting to see Ryan home started our house 2days after we had our pre-construction meeting with our PM.